The Overseas Passenger Terminal (OPT) on Clyde Quay Wharf occupies a prominent site on Wellington’s waterfront.

Adjacent to Chaffers Marina, it enjoys uninterrupted city and harbour views, and is a well-known Wellington landmark.

Close by are Oriental Bay, Te Papa Tongarewa - Museum of New Zealand, Royal Port Nicholson Yacht Club and Clyde Quay Boat Harbour and the Courtenay Place entertainment precinct.  Wellington’s central business district is also only an easy 10-minute walk away.

Turning Cinderella Into A Princess

A proposal from Wellington firm Willis Bond and Company Ltd to redevelop the OPT was accepted by the Wellington City Council on 26 June 2007.  This will see the future of this landmark building secured.

Back to top

Background

The original concrete wharf of Clyde Quay was finished in 1910, and extended and widened in 1964 to enable the construction of the OPT.

 

 

The Overseas Passenger Terminal
under construction in 1964

However, as air travel rapidly took over the international travel market, the new building’s purpose as a terminal for overseas visitors and migrants was never fully realised.

Back to top

Over the years the OPT has been used variously as a function centre, office space, for restaurants and businesses serving the adjacent Chaffers Marina.

 

The Overseas Passenger Terminal in 2006

With eventual redevelopment always  in mind, the wharf and building have only ever had  routine maintenance carried out and age and the harsh marine environment have taken their toll.

The Wellington Waterfront Framework acknowledged the heritage values of the OPT and required that it be retained and developed.

In 2004, a Design Brief was prepared by the Wellington City Council’s Technical Advisory Group to develop the OPT and wharf. The Brief was presented to and approved by the City Council’s Waterfront Development Sub-committee in May 2004 and Wellington Waterfront Ltd (WWL) was given the go-ahead to seek development proposals. A great deal of interest in the development opportunity was shown from developers and investors within New Zealand and overseas.

Following a rigorous evaluation process, involving WWL and the Council’s Technical Advisory Group, the Willis Bond proposal designed by Athfield Architects Ltd was selected. It was considered to have best met the Design Brief and also offered a return that WWL could reinvest in waterfront public space.

Back to top

A structural upgrade has become urgent

Structural engineers have assessed the current condition of the OPT and wharf and concluded they are in poor condition, requiring approximately $10 million to save them from demolition and upgrade them to a standard acceptable under the Building Act 2004.

The original concrete wharf structure under the building footprint is now almost 100 years old and is in a parlous state.

 

Exposed concrete pile reinforcing

Back to top

The concrete wharf slab, deck beams and lattice bracing have been severely affected by the seawater environment – making the concrete crumble away in places, exposing the reinforcing.

 

Deterioration of roofing struts

Tests also indicate that a number of the piles were not originally installed deeply enough and are under-strength.

The timber wharf extensions and piles, built in the 1960s prior to construction of the terminal building, are getting narrower in parts due to tidal erosion. A small number of piles are completely rotten and require replacement. Some connecting bolts are severely rusted and also require replacement.

Seismic assessment of the existing structures has determined that under the terms of the Building Act 2004, the site can almost be described as Earthquake Prone. The seismic code requirements that come into effect in late 2006 mean significant upgrading must occur to ensure compliance.

The existing building above the wharf is also in need of repair with parts of the structure – including the roof – in a poor state.

Back to top

The Willis Bond proposal

The development proposal from Wellington’s Willis Bond and Company Ltd and its designers, Athfield Architects Ltd, features a design that carefully refurbishes and extends the existing wharf and terminal structures. Building as much as possible upon the existing fabric, the proposal provides a range of new indoor and outdoor spaces to allow viable and sustainable uses that support or complement public use of the wharf and promenade, revitalising an area that has never reached its full potential.

The focus has been to develop a contemporary and adaptable architectural framework that respects the OPT’s former use as a terminal building while providing for apartments on upper levels and a range of single and double height tenancies on the ground that service and complement public use and enjoyment of the whole Waitangi Precinct.

The building is in three main forms: The north and south ends, which include most of the new construction to strengthen the gateways to the wharf from the land and from the sea; and the long central portion. This part is refurbished in a manner that retains proportions, rhythms and elements of the existing building including the roof, spire and main structural elements.

Intrinsic to the overall design are nautical and marine themes that have always defined the building, with references to a ship’s hull, structural ribs, bridges, decks and attachments such as life boats and davits. As such, the long sides incorporate elements that are cantilevered or recessed creating shelter and visual interest along the length of the building.

Back to top

The building's uses

The concept proposal features up to 70 apartments on the upper levels of the building.

As with all new development on the waterfront, the ground floor has to be predominantly publicly accessible. A mix of restaurants will provide atmosphere and activity at the southern end of the wharf. A further 1,000-1,500 square metres have been set aside for WWL to ensure a range of other uses including space for marina services and the marina office and other public recreational activities.

A car park is proposed for beneath the wharf, ensuring vehicles belonging to OPT residents will be contained within the building area without encroaching into public space.

Back to top

Building heights

The existing building height is approximately 12 metres. Increases to the height and bulk of the building are conservative, ensuring impacts on neighbouring views are minimal. As this design is still at concept stage, exact heights are yet to be determined. However, at this stage the maximum heights are:

  • Northern end – 17 metres
  • Middle section (the main body of the building) – 15 metres
  • Southern end – 18 metres

Back to top

Car parking

Public vehicle access will be maintained around the perimeter of the building and approximately 28 public car parks will be provided on the wharf itself.

The car parking for OPT residents will be housed beneath the wharf in an ingeniously designed ‘box’. Not only does this remove a significant number of parks from the wharf, but the box also strengthens the wharf structure by adding to its rigidity.

Access to the car park under the wharf is via a cut-out in the wharf making mundane car access a feature of the design. The cut-out will also help to separate pedestrian and vehicle access.

Car parking for marina users will be provided for elsewhere within the Waitangi precinct.

Back to top

Developers to pay for upgrade

As outlined previously, the wharf piles and substructure supporting the wharf urgently need replacing, at a cost of around $16 million. In the Willis Bond proposal, the developers will take responsibility for this cost, and for upgrading the OPT and wharf structures to a standard acceptable under the Building Act 2004. This essential upgrade would otherwise need to be paid for by ratepayers.

 Back to top

A SUMMARY OF THE BENEFITS OF THE WILLIS BOND PROPOSAL

When examining the many benefits of this proposal, we believe that Wellington and Wellingtonians are the winners all around:

  • WWL retains ownership and control of the wharf deck so the public will still have access to walk, drive and fish, as they can now.
  • WWL retains control (head lease) over a large portion of the ground floor. Along with an expectation that all ground floor spaces on the waterfront will be predominantly for public use, WWL also has an ongoing commitment to provide facilities to service the adjacent marina.
  • The approximate $16 million cost of replacing the wharf piles and substructure supporting the wharf will be borne by the developer, not city ratepayers.
  • The proposal offers Wellington an asset worthy of its location.
  • Most of the site’s heritage qualities will be maintained in this design.
  • Increases to height and bulk have been kept to a minimum (especially when compared with other, unsuccessful, proposals), thereby limiting the impact on views.
  • The development and its accompanying attractions will revitalise the area.
  • The nature and timeframe of this project present an opportunity to seek a range of tenants for the ground floor of the new building, as befits its prime Wellington location. We will be looking to include tenants offering public attractions that are not otherwise found in Wellington.
  • Development of the site to a building of this high quality design and use will ensure opportunities presented by the location of the site are not squandered and the wharf structure and the building remain attractive elements to the waterfront vista. The development has considered links with Waitangi Park, Chaffers Dock, the waterfront promenade, the Herd street development, the future Wardle buildings and Clyde Quay landscape.
  • The public space surrounding the building will be improved by resurfacing, new seating and lighting and better surveillance.
  • Approximately 28 car parks for public use will be provided on the wharf deck.
  • Ongoing access to the marina is maintained.
  • The money received from the lease will be invested by WWL into public works on the waterfront.

Back to top

WHERE TO FROM HERE?

  • September 2007 - Resource Consent Application lodged
    - granted by Greater Wellington Regional Council in May 2008
    but appeal lodged by Waterfront Watch - project now delayed pending a hearing in the Environment Court - this hearing has yet to be scheduled
  • Two years - Estimated construction period